25 Apr 2025
  • Utility relocation work is on-going.
  • Irrigation work is complete.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • Pierce Park will be closed on Saturday April 26th & Sunday April 27th for utility work.
  • Carlsbad Way will be closed from April 29th through May 6th for utility work and roadway work.