April 25, 2025
- Utility relocation work is on-going.
- Irrigation work is complete.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Pierce Park will be closed on Saturday April 26th & Sunday April 27th for utility work.
- Carlsbad Way will be closed from April 29th through May 6th for utility work and roadway work.
Share April 25, 2025 on Facebook
Share April 25, 2025 on Twitter
Share April 25, 2025 on Linkedin
Email April 25, 2025 link

Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends