August 20, 2026

  • The work zone is currently on the south side of State Street.
  • Left turns have been eliminated through the work zone.
  • Work on Pierce Park Lane is mostly complete.
  • Asphalt removal is complete on the south side of State Street.
  • Utility work for the project is complete.
  • Contractor working on stormwater facilities.
  • Placement of base gravels started August 3rd.
  • Concrete work for curb & gutter started August 18th and is on-going.
  • Concrete paving is anticipated to start in late August or early September.