August 20, 2026
- The work zone is currently on the south side of State Street.
- Left turns have been eliminated through the work zone.
- Work on Pierce Park Lane is mostly complete.
- Asphalt removal is complete on the south side of State Street.
- Utility work for the project is complete.
- Contractor working on stormwater facilities.
- Placement of base gravels started August 3rd.
- Concrete work for curb & gutter started August 18th and is on-going.
- Concrete paving is anticipated to start in late August or early September.