- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Westbound traffic is on the north side of State Street. Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
- Left turns have been eliminated through the work zone.
- Work on Pierce Park Lane is mostly complete.
- Utility work for the project is complete.
- Placement of base gravels started August 3rd and is on-going
- Concrete work for curb & gutter started August 18th and is on-going.
- Concrete paving is anticipated to start the week of August 31st.