August 29, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone. Contractor is excavating the north side of State Street.
- Underground electrical work is on-going.
- Work on stormwater system is on-going.
- Contractor placing base gravels for sidewalk and roadway.
- Concrete for sidewalk, curb, and gutter is expected to start the week of September 9th.
- Concrete paving is anticipated to start the week of September 22nd.