December 4, 2025
- Utility relocation work is complete for the first phase of work.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Underground electrical work is on-going for street lighting and for the new signal at Pierce Park.
- The new signal is anticipated to be operational in December or January.
- Concrete for sidewalk, curb, and gutter is complete on the east leg for this phase and on-going at the intersection and on the west leg.
- Asphalt paving is complete on the east side of the project for this phase and on-going at the north leg and on the west leg.
- Concrete paving is complete on the east leg and west leg for this phase, and on-going at the intersection and on the north leg. Work is weather dependent.
Share December 4, 2025 on Facebook
Share December 4, 2025 on Twitter
Share December 4, 2025 on Linkedin
Email December 4, 2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends