December 4, 2025
- Utility relocation work is complete for the first phase of work.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Underground electrical work is on-going for street lighting and for the new signal at Pierce Park.
- The new signal is anticipated to be operational in December or January.
- Concrete for sidewalk, curb, and gutter is complete on the east leg for this phase and on-going at the intersection and on the west leg.
- Asphalt paving is complete on the east side of the project for this phase and on-going at the north leg and on the west leg.
- Concrete paving is complete on the east leg and west leg for this phase, and on-going at the intersection and on the north leg. Work is weather dependent.
Share December 4, 2025 on Facebook
Share December 4, 2025 on X (formerly Twitter)
Share December 4, 2025 on Linkedin
Email December 4, 2025 link
This project is substantially complete.