February 12, 2026

  • Utility relocation work is complete for the first phase of work.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • The new signal at Pierce Park was activated the night of January 14th. Traffic on Pierce Park has been shifted onto the new concrete pavement on the west side of Pierce Park.
  • Contractor excavating for curb, gutter, sidewalk, and roadway on the east side of Pierce Park.
  • Concrete for sidewalk, curb, and gutter is complete on the east leg for this phase and on-going at the intersection and on the west leg.
  • Asphalt paving is anticipated to be complete for this phase in mid-March.
  • Concrete paving was completed for this phase on February 12th.
  • The traffic swap to the second phase of the project is anticipated for late March or early April.
  • Work is weather dependent.