February 19, 2026

  • Utility relocation work is complete for the first phase of work.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • The new signal at Pierce Park was activated the night of January 14th.
  • Traffic on Pierce Park has been shifted onto the new concrete pavement on the west side of Pierce Park.
  • Contractor excavating for curb, gutter, sidewalk, and roadway on the east side of Pierce Park.
  • Concrete for sidewalk, curb, and gutter is complete on the east leg for this phase and on-going at the intersection and on the west leg.
  • Asphalt paving is anticipated to be complete for this phase in mid-March.
  • Concrete paving was completed for this phase on February 12th.
  • The traffic swap to the second phase of the project is anticipated for late March or early April.
  • Work is weather dependent.