February 28, 2025

28 Feb 2025
  • Work began January 20th.
  • Contractor is removing trees, fence, and other obstructions.
  • Utility relocation work is on-going.
  • Irrigation work is on-going.
  • Traffic calming plan will be implemented in the neighborhoods north of State Street beginning the week of March 10th.
  • Traffic will be shifted to the south as early as March 19th & 20th.
Share February 28, 2025 on Facebook Share February 28, 2025 on Twitter Share February 28, 2025 on Linkedin Email February 28, 2025 link