July 11, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
- Underground electrical work is on-going.
- Work on stormwater system is anticipated to start the week of July 14th.
Share July 11, 2025 on Facebook
Share July 11, 2025 on Twitter
Share July 11, 2025 on Linkedin
Email July 11, 2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends