- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Contractor is excavating the north side of State Street. Some work is delayed pending utility work.
- Underground electrical work is on-going.
- Work on stormwater system is on-going.