July 2, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Contractor is excavating the north side of State Street. Some work is delayed pending utility work. Underground electrical work is on-going.
Share July 2, 2025 on Facebook
Share July 2, 2025 on X (formerly Twitter)
Share July 2, 2025 on Linkedin
Email July 2, 2025 link
This project is substantially complete.