- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Westbound traffic is on the north side of State Street.
- Eastbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st. The work zone is currently on the south side of State Street.
- Left turns have been eliminated through the work zone.
- Work on Pierce Park Lane is mostly complete.
- Asphalt removal is complete on the south side of State Street.
- Utility work for the project is complete.
- Contractor working on stormwater facilities.
- Placement of base gravels is anticipated to start the week of August 3rd.
- Concrete work anticipated to start in late August.