June 5, 2026

  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Eastbound traffic is on the south side of State Street.
  • Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
  • The work zone is currently on the south side of State Street.
  • Left turns have been eliminated through the work zone.
  • Work on Pierce Park Lane is mostly complete.
  • Asphalt removal has started on the south side of State Street. Utility work will follow.
Share June 5, 2026 on Facebook Share June 5, 2026 on X (formerly Twitter) Share June 5, 2026 on Linkedin Email June 5, 2026 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>