March 13, 2025
- Utility relocation work is complete for the first phase of work.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Hertford Way is scheduled to be closed the week of Spring Break, March 16th – 22nd for roadway excavation and asphalt paving.
- Contractor excavating for curb, gutter, sidewalk, and roadway on the east side of Pierce Park.
- Concrete for sidewalk, curb, and gutter is complete on the east leg for this phase and on-going at the intersection and on the west leg.
- Asphalt paving is anticipated to be complete for this phase in mid-March.
- Concrete paving was completed for this phase on February 12th.
- The traffic swap to the second phase of the project is anticipated for late March or early April.
- Work is weather dependent.
Share March 13, 2025 on Facebook
Share March 13, 2025 on Twitter
Share March 13, 2025 on Linkedin
Email March 13, 2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends