March 19, 2026

  • Utility relocation work is complete for the first phase of work.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • Hertford Way is scheduled to be closed the week of Spring Break, March 16th – 22nd for roadway excavation and asphalt paving.
  • Contractor excavating for curb, gutter, sidewalk, and roadway on the east side of Pierce Park.
  • Concrete for sidewalk, curb, and gutter is complete on State Street for this phase and on-going on Pierce Park.
  • Concrete paving was completed for this phase on February 12th.
  • Asphalt paving was completed for this phase on March 20th.
  • The traffic swap to the second phase of the project is tentatively scheduled for the night of March 31st.