May 21, 2026
- Traffic calming plan has been implemented in the neighborhoods north of State Street
- Eastbound traffic is on the south side of State Street. Westbound traffic was shifted onto the new pavement on the north side of State Street on the night of March 31st. The work zone is currently in the middle of State Street.
- Left turns have been eliminated through the work zone.
- Work on Pierce Park Lane is mostly complete.
- Asphalt and concrete paving for Phase 2 is complete.
- The traffic shift to the 3rd and final phase was implemented on the night of May 21st.