May 29, 2026

  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Eastbound traffic is on the south side of State Street.
  • Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
  • The work zone is currently on the south side of State Street.
  • Left turns have been eliminated through the work zone.
  • Work on Pierce Park Lane is mostly complete.
  • Asphalt removal has started on the south side of State Street.
  • Utility work will follow.