May 29, 2026
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Eastbound traffic is on the south side of State Street.
- Westbound traffic was shifted onto the new pavement in the middle of State Street on the night of May 21st.
- The work zone is currently on the south side of State Street.
- Left turns have been eliminated through the work zone.
- Work on Pierce Park Lane is mostly complete.
- Asphalt removal has started on the south side of State Street.
- Utility work will follow.