May 8, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Carlsbad Way will be closed from April 29th through May 6th for utility work and roadway work.
- Contractor is excavating the north side of State Street.
- Underground electrical work is on-going.