November 14, 2025

  • Utility relocation work is complete for the first phase of work.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • Underground electrical work is on-going for street lighting and for the new signal at Pierce Park.
  • Work on stormwater system is complete on the north side.
  • Contractor placing base gravels for sidewalk and roadway.
  • Concrete for sidewalk, curb, and gutter is on-going.
  • Concrete paving started on Friday, October 3rd and is on-going.
  • Asphalt paving will start as early as Saturday, November 15th, weather dependent.