November 20, 2025

  • Utility relocation work is complete for the first phase of work.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • Underground electrical work is on-going for street lighting and for the new signal at Pierce Park.
  • The new signal is anticipated to be operational in December or January.
  • Concrete for sidewalk, curb, and gutter is complete on the east leg for this phase and on-going at the intersection and on the west leg.
  • Asphalt paving is complete on the east side of the project for this phase and on-going at the north leg and on the west leg.
  • Concrete paving is complete on the east leg and west leg for this phase, and on-going at the intersection and on the north leg.
  • Work is weather dependent.