October 16, 2026
- Concrete work for curb, gutter, & sidewalk is nearly complete.
- Concrete paving and mainline asphalt paving are complete.
- Permanent striping and concrete island construction will be on-going throughout October.
- Traffic was shifted into its permanent configuration on October 16th.
- The left-turn lane at Pierce Park was opened October 16th.
- Minor work with daytime lane closures will continue into November, including swale construction, landscape repair, etc.