October 17, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Underground electrical work is on-going for street lighting and for the new signal at Pierce Park.
- Work on stormwater system is complete on the north side. Contractor placing base gravels for sidewalk and roadway.
- Concrete for sidewalk, curb, and gutter is on-going.
- Concrete paving started on Friday, October 3rd and is on-going.
Share October 17, 2025 on Facebook
Share October 17, 2025 on X (formerly Twitter)
Share October 17, 2025 on Linkedin
Email October 17, 2025 link
This project is substantially complete.