October 2, 2026
- Placement of base gravels started August 3rd and is on-going.
- Concrete work for curb & gutter started August 18th and is on-going.
- Concrete paving is complete.
- Mainline asphalt paving is complete.
- Permanent striping and concrete island construction is scheduled for October.
- The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
- Minor work will continue into November, including swale construction, landscape repair, etc.
Share October 2, 2026 on Facebook
Share October 2, 2026 on X (formerly Twitter)
Share October 2, 2026 on Linkedin
Email October 2, 2026 link
This project is substantially complete.