October 9, 2026
- Concrete work for curb, gutter, & sidewalk is nearly complete.
- Concrete paving and mainline asphalt paving are complete.
- Permanent striping and concrete island construction will be on-going throughout October.
- Traffic will be shifted into its permanent configuration as early as October 16th, weather dependent.
- The left-turn lane at Pierce Park is anticipated to re-open as early as October 16th, weather dependent.
- Minor work will continue into November, including swale construction, landscape repair, etc.
Share October 9, 2026 on Facebook
Share October 9, 2026 on X (formerly Twitter)
Share October 9, 2026 on Linkedin
Email October 9, 2026 link
This project is substantially complete.