September 11, 2026
- Utility work for the project is complete.
- Placement of base gravels started August 3rd and is on-going.
- Concrete work for curb & gutter started August 18th and is on-going.
- Concrete paving is complete.
- Asphalt paving is scheduled for late September.
- Permanent striping, concrete island construction, and swale construction is scheduled for October.
Share September 11, 2026 on Facebook
Share September 11, 2026 on X (formerly Twitter)
Share September 11, 2026 on Linkedin
Email September 11, 2026 link
This project is substantially complete.