September 12, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Underground electrical work is on-going.
- Work on stormwater system is on-going.
- Contractor placing base gravels for sidewalk and roadway.
- Concrete for sidewalk, curb, and gutter is expected to start the week of September 15th.
- Concrete paving is anticipated to start the week of September 22nd.
Share September 12, 2025 on Facebook
Share September 12, 2025 on X (formerly Twitter)
Share September 12, 2025 on Linkedin
Email September 12, 2025 link
This project is substantially complete.