September 12, 2025

  • Utility relocation work is on-going.
  • Traffic calming plan has been implemented in the neighborhoods north of State Street.
  • Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
  • Left turns have been eliminated through the work zone.
  • Underground electrical work is on-going.
  • Work on stormwater system is on-going.
  • Contractor placing base gravels for sidewalk and roadway.
  • Concrete for sidewalk, curb, and gutter is expected to start the week of September 15th.
  • Concrete paving is anticipated to start the week of September 22nd.