September 17, 2026

  • Placement of base gravels started August 3rd and is on-going.
  • Concrete work for curb & gutter started August 18th and is on-going.
  • Concrete paving is complete.
  • Asphalt paving is scheduled for late September or early October.
  • Permanent striping and concrete island construction is scheduled for October.
  • The left-turn lane at Pierce Park is anticipated to re-open by the end of October.
  • Minor work will continue into November, including swale construction, landscape repair, etc.