September 26, 2025
- Utility relocation work is on-going.
- Traffic calming plan has been implemented in the neighborhoods north of State Street.
- Traffic has been shifted to the south so the Contractor can construct the north side of State Street.
- Left turns have been eliminated through the work zone.
- Underground electrical work is on-going.
- Work on stormwater system is complete on the north side.
- Contractor placing base gravels for sidewalk and roadway.
- Concrete for sidewalk, curb, and gutter is on-going.
- Concrete paving is anticipated to start on Friday, October 3rd.