September 3, 2026
- Work on Pierce Park Lane is mostly complete.
- Utility work for the project is complete.
- Placement of base gravels started August 3rd and is on-going.
- Concrete work for curb & gutter started August 18th and is on-going.
- Concrete paving started September 1st and will be complete by mid-September.
- Asphalt paving is scheduled for late September.