The Ada County Highway District (ACHD) is constructing improvements for Stoddard Road between Victory and Overland. The purpose of this project is to improve traffic flow and increase safety for all users.

Project Description

  • Widen Stoddard, from Victory to Overland to three lanes and install center medians where the center turn lane is not needed for access.
  • Widen the existing bridge over the Ridenbaugh Canal.
  • Construct curb, gutter, and bike lanes on both sides of the road.
  • Relocate the existing Pedestrian Hybrid Beacon (PHB) to align with Victory Middle School and install two more enhanced pedestrian crossings in the project area.
    • A new crosswalk with a Rapid Rectangular Flashing Beacon (RRFB) on Stoddard Road, north of Ridenbaugh canal.
    • A new Pedestrian Hybrid Beacon (PHB) and crosswalk on the west leg of Victory Road near the Stoddard Road intersection.
  • Add a 10-foot-wide multi-use pathway on the west side of Stoddard between Victory and Kodiak. The pathway will continue on the south side of Kodiak.

The Ada County Highway District (ACHD) is constructing improvements for Stoddard Road between Victory and Overland. The purpose of this project is to improve traffic flow and increase safety for all users.

Project Description

  • Widen Stoddard, from Victory to Overland to three lanes and install center medians where the center turn lane is not needed for access.
  • Widen the existing bridge over the Ridenbaugh Canal.
  • Construct curb, gutter, and bike lanes on both sides of the road.
  • Relocate the existing Pedestrian Hybrid Beacon (PHB) to align with Victory Middle School and install two more enhanced pedestrian crossings in the project area.
    • A new crosswalk with a Rapid Rectangular Flashing Beacon (RRFB) on Stoddard Road, north of Ridenbaugh canal.
    • A new Pedestrian Hybrid Beacon (PHB) and crosswalk on the west leg of Victory Road near the Stoddard Road intersection.
  • Add a 10-foot-wide multi-use pathway on the west side of Stoddard between Victory and Kodiak. The pathway will continue on the south side of Kodiak.
  • Stoddard Road Construction to Start Soon

    Share Stoddard Road Construction to Start Soon on Facebook Share Stoddard Road Construction to Start Soon on X (formerly Twitter) Share Stoddard Road Construction to Start Soon on Linkedin Email Stoddard Road Construction to Start Soon link

    Starting as early as mid-November, the Ada County Highway District (ACHD) will start construction on the Stoddard Road, Victory Road to Overland Road project. The purpose of this project is to improve traffic flow and increase safety for all users. Work is expected to be complete in fall 2027.*

    Traffic and Construction Impacts

    • Lane restrictions with flaggers
    • Significant utility work is expected
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize impacts and maintain access

    *Construction schedules may change.

    Starting as early as mid-November, the Ada County Highway District (ACHD) will start construction on the Stoddard Road, Victory Road to Overland Road project. The purpose of this project is to improve traffic flow and increase safety for all users. Work is expected to be complete in fall 2027.*

    Traffic and Construction Impacts

    • Lane restrictions with flaggers
    • Significant utility work is expected
    • General construction noise, dust, equipment backup alarms and ground vibration
    • Crews will work from 7 a.m. to 7 p.m. unless otherwise approved
    • The contractor will work with property owners to minimize impacts and maintain access

    *Construction schedules may change.

  • Winter 2023 Public Comment Summary

    Share Winter 2023 Public Comment Summary on Facebook Share Winter 2023 Public Comment Summary on X (formerly Twitter) Share Winter 2023 Public Comment Summary on Linkedin Email Winter 2023 Public Comment Summary link

    The Ada County Highway District (ACHD) hosted a virtual public outreach event soliciting public comment for the Stoddard Road, Victory Road to Overland Road project, from February 2, 2023 to February 16, 2023. View the public comment summary and infographic below!

    The Ada County Highway District (ACHD) hosted a virtual public outreach event soliciting public comment for the Stoddard Road, Victory Road to Overland Road project, from February 2, 2023 to February 16, 2023. View the public comment summary and infographic below!

Page last updated: 21 Oct 2026, 03:29 PM