Suntree Place and Old Oak Avenue Storm Drain Project

Share Suntree Place and Old Oak Avenue Storm Drain Project on Facebook Share Suntree Place and Old Oak Avenue Storm Drain Project on Twitter Share Suntree Place and Old Oak Avenue Storm Drain Project on Linkedin Email Suntree Place and Old Oak Avenue Storm Drain Project link

This project is substantially complete.

The Ada County Highway District (ACHD) will begin construction on Old Oak Avenue and the Suntree Place cul-de-sac in early July of 2024. Construction is expected to be completed in early September 2024.

Improvements include constructing two new seepage beds to help mitigate historical flooding in the area.

The work may include, but is not limited to, the following impacts:

  • Temporary pedestrian detours
  • General construction noise
  • Dust
  • Equipment backup alarms and ground vibration

No full road closures are anticipated; however, lane restrictions and flaggers will be present throughout the project. Residents and adjacent property owners will have access during construction. Emergency access will be accommodated if the need arises.

Regular construction hours are planned between 7:00 am and 6:00 pm Monday through Friday.

The Ada County Highway District (ACHD) will begin construction on Old Oak Avenue and the Suntree Place cul-de-sac in early July of 2024. Construction is expected to be completed in early September 2024.

Improvements include constructing two new seepage beds to help mitigate historical flooding in the area.

The work may include, but is not limited to, the following impacts:

  • Temporary pedestrian detours
  • General construction noise
  • Dust
  • Equipment backup alarms and ground vibration

No full road closures are anticipated; however, lane restrictions and flaggers will be present throughout the project. Residents and adjacent property owners will have access during construction. Emergency access will be accommodated if the need arises.

Regular construction hours are planned between 7:00 am and 6:00 pm Monday through Friday.

This project is substantially complete.

  • August 9, 2024

    Share August 9, 2024 on Facebook Share August 9, 2024 on Twitter Share August 9, 2024 on Linkedin Email August 9, 2024 link
    • Contractor started excavating on Suntree July 17th.
    • Work on Suntree complete, minus paving which will be done at the same time as Old Oak, this week.
    • Old Oak demo complete.
    • Prep for paving complete.
    • Paving is scheduled for this week.
  • August 2, 2024

    Share August 2, 2024 on Facebook Share August 2, 2024 on Twitter Share August 2, 2024 on Linkedin Email August 2, 2024 link
    • Contractor started excavating on Suntree July 17th - Work on Suntree complete, minus paving which will be done at the same time as Old Oak, next week.
    • Old Oak demo complete. Prep for paving complete. Paving is scheduled for early next week.
  • July 26, 2024

    Share July 26, 2024 on Facebook Share July 26, 2024 on Twitter Share July 26, 2024 on Linkedin Email July 26, 2024 link
    • Contractor started excavating on Suntree July 17th.
    • Work on Suntree complete, minus paving which will be done at the same time as Old Oak, next week.
    • Old Oak demo started.
  • July 12, 2024

    Share July 12, 2024 on Facebook Share July 12, 2024 on Twitter Share July 12, 2024 on Linkedin Email July 12, 2024 link
    • Notice to proceed is anticipated for July.
    • Under redesign due to water table being too high.