-
Share May 10, 2024 on Facebook
Share May 10, 2024 on X (formerly Twitter)
Share May 10, 2024 on Linkedin
Email May 10, 2024 link
Project substantially complete.
Project substantially complete.
Project substantially complete
-
Share April 19, 2024 on Facebook
Share April 19, 2024 on X (formerly Twitter)
Share April 19, 2024 on Linkedin
Email April 19, 2024 link
- Asphalt paving complete.
- Minor work remains.
- Asphalt paving complete.
- Minor work remains.
Project substantially complete
-
Share April 12, 2024 on Facebook
Share April 12, 2024 on X (formerly Twitter)
Share April 12, 2024 on Linkedin
Email April 12, 2024 link
- Road base prep complete.
- Contractor paved April 10th.
- Road base prep complete.
- Contractor paved April 10th.
Project substantially complete
-
Share April 5, 2024 on Facebook
Share April 5, 2024 on X (formerly Twitter)
Share April 5, 2024 on Linkedin
Email April 5, 2024 link
- Road base prep complete.
- Contractor is tentatively planning to pave next week.
- Road base prep complete.
- Contractor is tentatively planning to pave next week.
Project substantially complete
-
Share March 29, 2024 on Facebook
Share March 29, 2024 on X (formerly Twitter)
Share March 29, 2024 on Linkedin
Email March 29, 2024 link
- Road base prep has started.
- Road base prep has started.
Project substantially complete
-
Share March 21, 2024 on Facebook
Share March 21, 2024 on X (formerly Twitter)
Share March 21, 2024 on Linkedin
Email March 21, 2024 link
- Backfill complete around the structure.
- Rip Rap is installed.
- Prep for curb and gutter ongoing.
- Backfill complete around the structure.
- Rip Rap is installed.
- Prep for curb and gutter ongoing.
Project substantially complete
-
Share March 15, 2024 on Facebook
Share March 15, 2024 on X (formerly Twitter)
Share March 15, 2024 on Linkedin
Email March 15, 2024 link
- Waterproofing complete.
- Backfill complete around the structure.
- Prep for curb and gutter started.
- Waterproofing complete.
- Backfill complete around the structure.
- Prep for curb and gutter started.
Project substantially complete
-
Share March 8, 2024 on Facebook
Share March 8, 2024 on X (formerly Twitter)
Share March 8, 2024 on Linkedin
Email March 8, 2024 link
- Waterproofing complete.
- Backfill continues around the structure.
- Precast sections received.
- Prep for curb and gutter started.
- Waterproofing complete.
- Backfill continues around the structure.
- Precast sections received.
- Prep for curb and gutter started.
Project substantially complete
-
Share March 1, 2024 on Facebook
Share March 1, 2024 on X (formerly Twitter)
Share March 1, 2024 on Linkedin
Email March 1, 2024 link
- Prep for waterproofing complete.
- Backfill started around the structure.
- Prep for waterproofing complete.
- Backfill started around the structure.
Project substantially complete
-
Share February 23, 2024 on Facebook
Share February 23, 2024 on X (formerly Twitter)
Share February 23, 2024 on Linkedin
Email February 23, 2024 link
- Precast sections complete.
- Wall pours complete.
- Prep for waterproofing started.
- Precast sections complete.
- Wall pours complete.
- Prep for waterproofing started.
Project substantially complete