Project substantially complete

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Topaz Avenue north of Overland Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Five Mile Creek.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Topaz Avenue north of Overland Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.

This bridge improvement project will include removing and replacing the existing bridge over the Five Mile Creek.

*Construction schedules may change due to high demand for contractors, labor, and supplies.

Project substantially complete

  • February 16, 2024

    Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link
    • Precast sections complete.
    • Wall pours scheduled for this week.
  • February 9, 2024

    Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link
    • Precast sections set and grouted.
    • Forming wing and end walls at both ends.
  • February 2, 2024

    Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link
    • Waiting on precast - 5 of 11 sections have been delivered.
    • Planning to set precast sections starting Friday.
    • Footings placed.
  • January 26, 2024

    Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link
    • Installation of the City of Meridian sewer casing complete.
    • Waiting on precast.
    • Excavation prep for footings complete.
    • Base prep for footings complete.
    • Contractor will prep for footing placements once weather permits.
  • January 19, 2024

    Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link
    • Installation of the City of Meridian sewer casing complete.
    • Waiting on precast.
    • Excavation prep for footings complete.
    • Base prep for footings complete.
    • Contractor is prepped for footing placements once weather permits.
  • January 12, 2024

    Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link
    • Installation of the City of Meridian sewer casing complete.
    • Waiting on precast.
    • Excavation prep for footings continues.
    • Base prep for footings started.
  • January 5, 2024

    Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link
    • Installation of the City of Meridian sewer casing complete.
    • Waiting on precast.
    • Excavation prep for footings started.
  • December 22, 2023

    Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link
    • Contractor has demoed the existing culvert.
    • Installation of the City of Meridian sewer casing nearly complete.
    • Waiting on precast.
  • December 15, 2023

    Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link
    • Contractor started Demo of the roadway on December 4 th.
    • Environmental plan being developed for City of Meridian work.
  • December 8, 2023

    Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link
    • Contractor to start on Topaz December 4th.
    • Notification boards have been set.
    • Environmental plan being developed for City of Meridian work.