January 19, 2024

  • Installation of the City of Meridian sewer casing complete.
  • Waiting on precast.
  • Excavation prep for footings complete.
  • Base prep for footings complete.
  • Contractor is prepped for footing placements once weather permits.
Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link

Project substantially complete