Topaz Avenue Bridge
Project substantially complete
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Topaz Avenue north of Overland Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.
This bridge improvement project will include removing and replacing the existing bridge over the Five Mile Creek.
*Construction schedules may change due to high demand for contractors, labor, and supplies.
As part of the Ada County Highway District’s (ACHD) Bridge Maintenance Program, ACHD will replace the culvert on Topaz Avenue north of Overland Road, as early as the beginning of November 2023.* Construction is expected to be complete spring of 2024.
This bridge improvement project will include removing and replacing the existing bridge over the Five Mile Creek.
*Construction schedules may change due to high demand for contractors, labor, and supplies.
Project substantially complete
-
February 16, 2024
Share February 16, 2024 on Facebook Share February 16, 2024 on Twitter Share February 16, 2024 on Linkedin Email February 16, 2024 link- Precast sections complete.
- Wall pours scheduled for this week.
- Precast sections complete.
- Wall pours scheduled for this week.
Project substantially complete
-
February 9, 2024
Share February 9, 2024 on Facebook Share February 9, 2024 on Twitter Share February 9, 2024 on Linkedin Email February 9, 2024 link- Precast sections set and grouted.
- Forming wing and end walls at both ends.
- Precast sections set and grouted.
- Forming wing and end walls at both ends.
Project substantially complete
-
February 2, 2024
Share February 2, 2024 on Facebook Share February 2, 2024 on Twitter Share February 2, 2024 on Linkedin Email February 2, 2024 link- Waiting on precast - 5 of 11 sections have been delivered.
- Planning to set precast sections starting Friday.
- Footings placed.
- Waiting on precast - 5 of 11 sections have been delivered.
- Planning to set precast sections starting Friday.
- Footings placed.
Project substantially complete
-
January 26, 2024
Share January 26, 2024 on Facebook Share January 26, 2024 on Twitter Share January 26, 2024 on Linkedin Email January 26, 2024 link- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings complete.
- Base prep for footings complete.
- Contractor will prep for footing placements once weather permits.
- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings complete.
- Base prep for footings complete.
- Contractor will prep for footing placements once weather permits.
Project substantially complete
-
January 19, 2024
Share January 19, 2024 on Facebook Share January 19, 2024 on Twitter Share January 19, 2024 on Linkedin Email January 19, 2024 link- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings complete.
- Base prep for footings complete.
- Contractor is prepped for footing placements once weather permits.
- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings complete.
- Base prep for footings complete.
- Contractor is prepped for footing placements once weather permits.
Project substantially complete
-
January 12, 2024
Share January 12, 2024 on Facebook Share January 12, 2024 on Twitter Share January 12, 2024 on Linkedin Email January 12, 2024 link- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings continues.
- Base prep for footings started.
- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings continues.
- Base prep for footings started.
Project substantially complete
-
January 5, 2024
Share January 5, 2024 on Facebook Share January 5, 2024 on Twitter Share January 5, 2024 on Linkedin Email January 5, 2024 link- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings started.
- Installation of the City of Meridian sewer casing complete.
- Waiting on precast.
- Excavation prep for footings started.
Project substantially complete
-
December 22, 2023
Share December 22, 2023 on Facebook Share December 22, 2023 on Twitter Share December 22, 2023 on Linkedin Email December 22, 2023 link- Contractor has demoed the existing culvert.
- Installation of the City of Meridian sewer casing nearly complete.
- Waiting on precast.
- Contractor has demoed the existing culvert.
- Installation of the City of Meridian sewer casing nearly complete.
- Waiting on precast.
Project substantially complete
-
December 15, 2023
Share December 15, 2023 on Facebook Share December 15, 2023 on Twitter Share December 15, 2023 on Linkedin Email December 15, 2023 link- Contractor started Demo of the roadway on December 4 th.
- Environmental plan being developed for City of Meridian work.
- Contractor started Demo of the roadway on December 4 th.
- Environmental plan being developed for City of Meridian work.
Project substantially complete
-
December 8, 2023
Share December 8, 2023 on Facebook Share December 8, 2023 on Twitter Share December 8, 2023 on Linkedin Email December 8, 2023 link- Contractor to start on Topaz December 4th.
- Notification boards have been set.
- Environmental plan being developed for City of Meridian work.
- Contractor to start on Topaz December 4th.
- Notification boards have been set.
- Environmental plan being developed for City of Meridian work.
Project substantially complete
Who's Listening
-
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org