April 10, 2026

  • Black Cat remains closed south of Ustick Rd – Anticipated re-opening by the end of April.
  • City of Meridian sewer and water line installation is complete.
  • Water Control Vault commissioning work is ongoing.
  • Underground electrical work and signal pole bases are complete.
  • The electrical contractor is working on the wiring in the signal cabinets.
  • Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, are complete.
  • Concrete sidewalk placements on South Black Cat are complete.
  • Concrete pavement on the south leg of Black Cat will be completed this week.
  • Contractor is tentatively planning to finish the asphalt paving the week of April 20.
Share April 10, 2026 on Facebook Share April 10, 2026 on X (formerly Twitter) Share April 10, 2026 on Linkedin Email April 10, 2026 link

This project is substantially complete.