Ustick Road, Black Cat Road to Ten Mile Road

Share Ustick Road, Black Cat Road to Ten Mile Road on Facebook Share Ustick Road, Black Cat Road to Ten Mile Road on Twitter Share Ustick Road, Black Cat Road to Ten Mile Road on Linkedin Email Ustick Road, Black Cat Road to Ten Mile Road link

The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.

Ustick, Black Cat to Ten Mile

  • Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
  • Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
  • Add a traffic signal at Naomi Avenue.
  • Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
  • Upgrade stormwater facilities and replace irrigation pipes.

Ustick and Black Cat Intersection

  • Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
  • Add dedicated right and left turn lanes on all approaches.
  • Install curb, gutter, and multi-use pathways.

The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.

Ustick, Black Cat to Ten Mile

  • Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
  • Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
  • Add a traffic signal at Naomi Avenue.
  • Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
  • Upgrade stormwater facilities and replace irrigation pipes.

Ustick and Black Cat Intersection

  • Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
  • Add dedicated right and left turn lanes on all approaches.
  • Install curb, gutter, and multi-use pathways.
  • January 23, 2025

    Share January 23, 2025 on Facebook Share January 23, 2025 on Twitter Share January 23, 2025 on Linkedin Email January 23, 2025 link
    • Black Cat Road is closed south of Ustick Road.
    • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
    • Irrigation and seepage bed installation is ongoing.
    • Roadway and sidewalk demo and prep is ongoing.
    • Eight mile irrigation box on Black Cat has been demolished.
    • Excavation for the west side headwall to start this week.
    • Precast box fabrication ongoing.
  • January 17, 2025

    Share January 17, 2025 on Facebook Share January 17, 2025 on Twitter Share January 17, 2025 on Linkedin Email January 17, 2025 link
    • Black Cat Road is closed south of Ustick Road.
    • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
    • Irrigation and seepage bed installation is ongoing.
    • Roadway and sidewalk demo and prep is ongoing.
    • Eight mile irrigation box on Black Cat has been demolished.
    • Excavation for the west side headwall to start this week.
    • Precast box fabrication started this week.
  • January 10, 2024

    Share January 10, 2024 on Facebook Share January 10, 2024 on Twitter Share January 10, 2024 on Linkedin Email January 10, 2024 link
    • Black Cat Road is closed south of Ustick Road.
    • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
    • Irrigation and seepage bed installation is ongoing.
    • Roadway and sidewalk demo and prep is ongoing.
    • Eight Mile irrigation box on Black Cat has been demolished.
    • Excavation for the west side headwall to start this week.
    • Precast box fabrication started this week.
  • January 3, 2025

    Share January 3, 2025 on Facebook Share January 3, 2025 on Twitter Share January 3, 2025 on Linkedin Email January 3, 2025 link
    • Black Cat Road is closed south of Ustick Road.
    • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
    • Irrigation and seepage bed installation is ongoing.
    • Roadway and sidewalk demo and prep is ongoing.
    • Eight Mile irrigation box on Black Cat has been demolished.
  • December 20, 2024

    Share December 20, 2024 on Facebook Share December 20, 2024 on Twitter Share December 20, 2024 on Linkedin Email December 20, 2024 link
    • Black Cat Road is closed south of Ustick Road.
    • Temporary asphalt for the new traffic pattern on the south side of Ustick complete.
    • Traffic will shift this week.
    • Irrigation and seepage bed install ongoing.
    • Roadway and sidewalk demo and prep ongoing.
    • Eight mile irrigation box on Black Cat has been demolished.
  • December 12, 2024

    Share December 12, 2024 on Facebook Share December 12, 2024 on Twitter Share December 12, 2024 on Linkedin Email December 12, 2024 link
    • Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
    • Temporary asphalt will be placed this week for the new traffic pattern on the south side of Ustick.
    • Irrigation and seepage bed install ongoing.
    • Roadway and sidewalk demo ongoing.
    • Eight Mile irrigation box on Black Cat has been demolished.
  • December 6, 2024

    Share December 6, 2024 on Facebook Share December 6, 2024 on Twitter Share December 6, 2024 on Linkedin Email December 6, 2024 link
    • Black Cat Road is closed south of Ustick Road.
    • Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
    • Prepping for temporary asphalt.
    • Irrigation and seepage bed install has started.
    • Demo ongoing.
  • November 22, 2024

    Share November 22, 2024 on Facebook Share November 22, 2024 on Twitter Share November 22, 2024 on Linkedin Email November 22, 2024 link
    • Contractor has completed implementing traffic control on the project and throughout the southern neighborhoods.
    • Black Cat Road is closed south of Ustick Road.
    • Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
  • November 15, 2024

    Share November 15, 2024 on Facebook Share November 15, 2024 on Twitter Share November 15, 2024 on Linkedin Email November 15, 2024 link
    • Contractor has started implementing traffic control on the project and throughout the southern neighborhoods.
    • Black Cat Road is closed south of Ustick Road.
    • Contractor milling the south half of the road in preparation for utility relocations and temporary pavement.
  • November 7, 2024

    Share November 7, 2024 on Facebook Share November 7, 2024 on Twitter Share November 7, 2024 on Linkedin Email November 7, 2024 link
    • Anticipated notice to proceed with construction on Monday, November 11th.
Page last updated: 23 Jan 2025, 12:10 PM