Ustick Road, Black Cat Road to Ten Mile Road
Share Ustick Road, Black Cat Road to Ten Mile Road on Facebook
Share Ustick Road, Black Cat Road to Ten Mile Road on Twitter
Share Ustick Road, Black Cat Road to Ten Mile Road on Linkedin
Email Ustick Road, Black Cat Road to Ten Mile Road link
The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.
Ustick, Black Cat to Ten Mile
- Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
- Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
- Add a traffic signal at Naomi Avenue.
- Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
- Upgrade stormwater facilities and replace irrigation pipes.
Ustick and Black Cat Intersection
- Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
- Add dedicated right and left turn lanes on all approaches.
- Install curb, gutter, and multi-use pathways.
-
February 7, 2025
Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall complete.
- Headwall is installed.
- Precast box fabrication ongoing.
-
January 31, 2025
Share January 31, 2025 on Facebook Share January 31, 2025 on Twitter Share January 31, 2025 on Linkedin Email January 31, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication ongoing.
-
January 23, 2025
Share January 23, 2025 on Facebook Share January 23, 2025 on Twitter Share January 23, 2025 on Linkedin Email January 23, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication ongoing.
-
January 17, 2025
Share January 17, 2025 on Facebook Share January 17, 2025 on Twitter Share January 17, 2025 on Linkedin Email January 17, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication started this week.
-
January 10, 2024
Share January 10, 2024 on Facebook Share January 10, 2024 on Twitter Share January 10, 2024 on Linkedin Email January 10, 2024 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall to start this week.
- Precast box fabrication started this week.
-
January 3, 2025
Share January 3, 2025 on Facebook Share January 3, 2025 on Twitter Share January 3, 2025 on Linkedin Email January 3, 2025 link- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
-
December 20, 2024
Share December 20, 2024 on Facebook Share December 20, 2024 on Twitter Share December 20, 2024 on Linkedin Email December 20, 2024 link- Black Cat Road is closed south of Ustick Road.
- Temporary asphalt for the new traffic pattern on the south side of Ustick complete.
- Traffic will shift this week.
- Irrigation and seepage bed install ongoing.
- Roadway and sidewalk demo and prep ongoing.
- Eight mile irrigation box on Black Cat has been demolished.
-
December 12, 2024
Share December 12, 2024 on Facebook Share December 12, 2024 on Twitter Share December 12, 2024 on Linkedin Email December 12, 2024 link- Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
- Temporary asphalt will be placed this week for the new traffic pattern on the south side of Ustick.
- Irrigation and seepage bed install ongoing.
- Roadway and sidewalk demo ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
-
December 6, 2024
Share December 6, 2024 on Facebook Share December 6, 2024 on Twitter Share December 6, 2024 on Linkedin Email December 6, 2024 link- Black Cat Road is closed south of Ustick Road.
- Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
- Prepping for temporary asphalt.
- Irrigation and seepage bed install has started.
- Demo ongoing.
-
November 22, 2024
Share November 22, 2024 on Facebook Share November 22, 2024 on Twitter Share November 22, 2024 on Linkedin Email November 22, 2024 link- Contractor has completed implementing traffic control on the project and throughout the southern neighborhoods.
- Black Cat Road is closed south of Ustick Road.
- Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
Page last updated: 07 Feb 2025, 12:47 PM
Follow Project
Stay informed
Subscribe for project updates
49 members of your community are following this project
Spring 2023 Public Outreach
-
Spring 2023 Public Outreach
-
Infographic, Spring 2023 Outreach (Ustick, Black Cat to Ten Mile) (222 KB) (pdf)
-
Comment Summary, Spring 2023 (Ustick, Black Cat to Ten Mile) (1.29 MB) (pdf)
-
Informational Slides (Ustick, Black Cat to Ten Mile) (18.9 MB) (pdf)
-
Project Design (Ustick, Black Cat to Ten Mile) (11.6 MB) (pdf)
-
Typical Sections (Ustick, Black Cat to Ten Mile) (559 KB) (pdf)
-
Timeline
-
2021
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageDesign started
-
Fall 2022
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #1
-
Spring 2023
Ustick Road, Black Cat Road to Ten Mile Road has finished this stagePublic input opportunity #2
-
2024
Ustick Road, Black Cat Road to Ten Mile Road has finished this stageBegin purchasing property necessary for project
-
November 2024
Ustick Road, Black Cat Road to Ten Mile Road is currently at this stageStart construction
-
Spring 2026
this is an upcoming stage for Ustick Road, Black Cat Road to Ten Mile RoadFinish construction
Related projects
Who's Listening
-
Senior Project Manager
Phone 208-387-6100 Email projects@achdidaho.org -
Construction Coordinator
Phone 208-387-6100 Email projects@achdidaho.org -
Business & Community Relations Coordinator
Phone 208-387-6100 Email ejohansen@achdidaho.org