Ustick Road, Black Cat Road to Ten Mile Road

Share Ustick Road, Black Cat Road to Ten Mile Road on Facebook Share Ustick Road, Black Cat Road to Ten Mile Road on Twitter Share Ustick Road, Black Cat Road to Ten Mile Road on Linkedin Email Ustick Road, Black Cat Road to Ten Mile Road link

The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.

Ustick, Black Cat to Ten Mile

  • Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
  • Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
  • Add a traffic signal at Naomi Avenue.
  • Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
  • Upgrade stormwater facilities and replace irrigation pipes.

Ustick and Black Cat Intersection

  • Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
  • Add dedicated right and left turn lanes on all approaches.
  • Install curb, gutter, and multi-use pathways.

The Ada County Highway District (ACHD) will be reconstructing Ustick Road between Black Cat Road and Ten Mile Road. The purpose of this project is to improve traffic flow and increase safety for all users.

Ustick, Black Cat to Ten Mile

  • Widen Ustick Road to two lanes in each direction, with center turn lanes or center medians at key locations.
  • Construct curb, gutter, and a 10-foot-wide multi-use pathway with a safety buffer on both sides of the roadway for pedestrian and bicyclists.
  • Add a traffic signal at Naomi Avenue.
  • Install an enhanced pedestrian crossing across Ustick Road at the Nine Mile Pathway.
  • Upgrade stormwater facilities and replace irrigation pipes.

Ustick and Black Cat Intersection

  • Widen the Ustick Road and Black Cat Road intersection to include additional through lanes.
  • Add dedicated right and left turn lanes on all approaches.
  • Install curb, gutter, and multi-use pathways.
  • February 19, 2026

    Share February 19, 2026 on Facebook Share February 19, 2026 on Twitter Share February 19, 2026 on Linkedin Email February 19, 2026 link
    • Black Cat remains closed south of Ustick Rd.
    • Concrete paving section, curb, gutter and sidewalk placements are nearly complete.
    • Remaining sections include the south side of Ustick and Black Cat.
    • Asphalt paving along Ustick complete and nearly all lanes have been marked.
    • Ustick and Black Cat signal swap to final configuration was completed this week.
    • City of Meridian sewer and water line installation is complete. Water Control Vault commissioning work has started.
    • Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, starting soon – prepped and waiting for better weather to place.
  • February 12, 2026

    Share February 12, 2026 on Facebook Share February 12, 2026 on Twitter Share February 12, 2026 on Linkedin Email February 12, 2026 link
    • Black Cat remains closed south of Ustick Rd.
    • Concrete paving section, curb, gutter and sidewalk placements are nearly complete.
    • Remaining sections include the south side of Ustick and Black Cat.
    • Asphalt paving along Ustick complete and nearly all lanes have been marked.
    • Ustick and Black Cat signal swap to final configuration was completed this week.
    • City of Meridian sewer and water line installation is complete.
    • Water Control Vault commissioning work has started.
    • Final remaining sections of concrete curb and gutter/sidewalk, along the eastern portion of Ustick, starting soon.
  • February 5, 2026

    Share February 5, 2026 on Facebook Share February 5, 2026 on Twitter Share February 5, 2026 on Linkedin Email February 5, 2026 link
    • Black Cat remains closed south of Ustick Rd.
    • Concrete paving section, curb, gutter and sidewalk placements are nearly complete.
    • Remaining sections include the south side of Ustick and Black Cat.
    • Asphalt paving along Ustick complete and nearly all lanes have been marked.
    • Ustick and Black Cat signal swap to final configuration was completed this week.
    • City of Meridian sewer and water line installation is complete.
    • Placing nine pole bases this week for signals.
  • January 30, 2026

    Share January 30, 2026 on Facebook Share January 30, 2026 on Twitter Share January 30, 2026 on Linkedin Email January 30, 2026 link
    • Eightmile and Ninemile irrigation: Irrigation work: Ninemile complete. Eightmile complete.
    • Curb, gutter and sidewalk placements are nearly complete.
    • Remaining sections include the east end of the project along Ustick – minimal work remains.
    • Patterned concrete median islands have been placed along Ustick – work ongoing on the south side of Black Cat.
    • Asphalt paving along Ustick complete and nearly all lanes have been marked.
    • Ustick and Black Cat signal swap to final configuration was completed this week.
    • City of Meridian sewer and water line installation is complete.
  • January 23, 2026

    Share January 23, 2026 on Facebook Share January 23, 2026 on Twitter Share January 23, 2026 on Linkedin Email January 23, 2026 link
    • Eightmile and Ninemile irrigation: Irrigation work: Ninemile complete.
    • Eightmile complete.
    • Curb, gutter and sidewalk placements are nearly complete.
    • Remaining sections include the east end of the project along Ustick – minimal work remains.
    • Patterned concrete median islands have been placed along Ustick – work ongoing on the south side of Black Cat.
    • Asphalt paving along Ustick complete and nearly all lanes have been marked.
    • Ustick and Black Cat signal swap to final configuration was completed this week.
    • City of Meridian sewer and water line installation is complete.
  • January 16, 2026

    Share January 16, 2026 on Facebook Share January 16, 2026 on Twitter Share January 16, 2026 on Linkedin Email January 16, 2026 link
    • Eightmile and Ninemile irrigation:
      • Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
      • Ninemile north headwall placed and backfilled. Eightmile has been backfilled.
    • Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
    • Patterned concrete median islands are being placed east of Black Cat.
    • Asphalt paving portions of the north and south side of Ustick complete.
    • Weather dependent, the contractor is working towards having the remaining paving sections on Ustick complete in the next couple of weeks.
    • City of Meridian sewer and water line installation is complete.
    • East headwall of Eightmile has been placed and backfilled.
  • January 9, 2026

    Share January 9, 2026 on Facebook Share January 9, 2026 on Twitter Share January 9, 2026 on Linkedin Email January 9, 2026 link
    • Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
    • Ninemile north headwall placed and backfilled. Eightmile has been backfilled.
    • Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
    • Patterned concrete median islands are being placed east of Black Cat.
    • Asphalt paving portions of the north and south side of Ustick complete.
    • Weather dependent, the contractor is working towards having the remaining paving sections on Ustick complete in the next couple of weeks.
    • City of Meridian sewer and water line installation is complete.
    • East headwall of Eightmile has been placed and backfilled.
  • December 18, 2025

    Share December 18, 2025 on Facebook Share December 18, 2025 on Twitter Share December 18, 2025 on Linkedin Email December 18, 2025 link
    • Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
    • Ninemile north headwall will be placed this week. Contractor anticipates having it backfilled before the holidays.
    • Eightmile has been backfilled.
    • Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
    • Patterned concrete median islands are being placed east of Black Cat.
    • Asphalt paving portions of the north and south side of Ustick complete.
    • City of Meridian sewer and water line installation complete – service tie-in to southeast property still pending.
    • Concrete paving south side of Ustick and Black Cat intersection is nearly complete. After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume – weather permitting.
  • December 11, 2025

    Share December 11, 2025 on Facebook Share December 11, 2025 on Twitter Share December 11, 2025 on Linkedin Email December 11, 2025 link
    • Irrigation and seepage bed installation is nearly complete.
    • Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
    • Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
    • Patterned concrete median islands are being placed east of Black Cat.
    • Asphalt paving portions of the north and south side of Ustick complete.
    • City of Meridian sewer and water line installation complete – service tie-in to southeast property still pending.
    • Concrete paving south side of Ustick and Black Cat intersection is nearly complete.
    • After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume.
  • December 4, 2025

    Share December 4, 2025 on Facebook Share December 4, 2025 on Twitter Share December 4, 2025 on Linkedin Email December 4, 2025 link
    • Irrigation and seepage bed installation is nearly complete.
    • Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
    • Patterned concrete median islands are being placed east of Black Cat.
    • Asphalt paving portions of the north and south side of Ustick complete. City of Meridian sewer and water line installation complete – service tie-in to SE property still pending. Concrete paving south side of Ustick and Black Cat intersection is nearly complete.
    • After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume.
Page last updated: 19 Feb 2026, 01:24 PM