April 2, 2026
- Black Cat remains closed south of Ustick Rd.
- City of Meridian sewer and water line installation is complete.
- Water Control Vault commissioning work is ongoing.
- Underground electrical work and signal pole bases are complete.
- Electrical contractor is working on the wiring in the signal cabinets.
- Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, are complete.
- Concrete sidewalk placements on South Black Cat are complete.
- Concrete pavement on the south leg of Black Cat is ongoing.
Share April 2, 2026 on Facebook
Share April 2, 2026 on X (formerly Twitter)
Share April 2, 2026 on Linkedin
Email April 2, 2026 link
This project is substantially complete.