April 4, 2025
- Black Cat Road is closed north of Ustick Road.
- Black Cat Road is open south of Ustick Road.
- Elmstone Ave, north of Ustick Road, will re-open on Monday morning, April 7th. Once Elmstone is open, Aspenstone Street will be closed at Black Cat Road.
- Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction. Irrigation and seepage bed installation is ongoing. Roadway and sidewalk demo and prep are ongoing on the north side of Ustick.
- Eight mile irrigation: Irrigation is complete for the season. Irrigation work, apart from Nine mile, is nearly complete in preparation for the City’s sewer bypass. Rutledge has been sleeved for sewer line install.
- Contractor is starting site prep and demo on N Black Cat – asphalt has been removed up to Aspenstone.