December 12, 2024

  • Contractor completed the milling of the south half of the road in preparation for utility relocations and temporary pavement.
  • Temporary asphalt will be placed this week for the new traffic pattern on the south side of Ustick.
  • Irrigation and seepage bed install ongoing.
  • Roadway and sidewalk demo ongoing.
  • Eight Mile irrigation box on Black Cat has been demolished.