December 18, 2025
- Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
- Ninemile north headwall will be placed this week. Contractor anticipates having it backfilled before the holidays.
- Eightmile has been backfilled.
- Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
- Patterned concrete median islands are being placed east of Black Cat.
- Asphalt paving portions of the north and south side of Ustick complete.
- City of Meridian sewer and water line installation complete – service tie-in to southeast property still pending.
- Concrete paving south side of Ustick and Black Cat intersection is nearly complete. After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume – weather permitting.
Share December 18, 2025 on Facebook
Share December 18, 2025 on Twitter
Share December 18, 2025 on Linkedin
Email December 18, 2025 link
Thank you for your contribution!
Help us reach out to more people in the community
Share this with family and friends