December 18, 2025

  • Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
  • Ninemile north headwall will be placed this week. Contractor anticipates having it backfilled before the holidays.
  • Eightmile has been backfilled.
  • Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
  • Patterned concrete median islands are being placed east of Black Cat.
  • Asphalt paving portions of the north and south side of Ustick complete.
  • City of Meridian sewer and water line installation complete – service tie-in to southeast property still pending.
  • Concrete paving south side of Ustick and Black Cat intersection is nearly complete. After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume – weather permitting.
Share December 18, 2025 on Facebook Share December 18, 2025 on Twitter Share December 18, 2025 on Linkedin Email December 18, 2025 link
#<Object:0x00007ff81a4f2800>