December 18, 2025
- Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
- Ninemile north headwall will be placed this week. Contractor anticipates having it backfilled before the holidays.
- Eightmile has been backfilled.
- Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
- Patterned concrete median islands are being placed east of Black Cat.
- Asphalt paving portions of the north and south side of Ustick complete.
- City of Meridian sewer and water line installation complete β service tie-in to southeast property still pending.
- Concrete paving south side of Ustick and Black Cat intersection is nearly complete. After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume β weather permitting.