December 4, 2025
- Irrigation and seepage bed installation is nearly complete.
- Eightmile and Ninemile irrigation: Irrigation work is ongoing at both Eightmile and Ninemile. Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
- Patterned concrete median islands are being placed east of Black Cat.
- Asphalt paving portions of the north and south side of Ustick complete. City of Meridian sewer and water line installation complete – service tie-in to SE property still pending. Concrete paving south side of Ustick and Black Cat intersection is nearly complete.
- After the irrigation work and water/sewer tie-in is complete, concrete paving of S. Black Cat will resume.
Share December 4, 2025 on Facebook
Share December 4, 2025 on X (formerly Twitter)
Share December 4, 2025 on Linkedin
Email December 4, 2025 link
This project is substantially complete.