February 14, 2025

14 Feb 2025
  • Black Cat Road is closed south of Ustick Road.
  • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
  • Irrigation and seepage bed installation is ongoing.
  • Roadway and sidewalk demo and prep is ongoing.
  • Eight Mile irrigation box on Black Cat has been demolished.
  • Excavation for the west side headwall complete.
  • Headwall is installed.
  • Precast box fabrication ongoing.
  • Southwest corner of Ustick and Black Cat irrigation work started.
Share February 14, 2025 on Facebook Share February 14, 2025 on Twitter Share February 14, 2025 on Linkedin Email February 14, 2025 link
#<Object:0x00000000324b0cf8>