February 14, 2025

  • Black Cat Road is closed south of Ustick Road.
  • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
  • Irrigation and seepage bed installation is ongoing.
  • Roadway and sidewalk demo and prep is ongoing.
  • Eight Mile irrigation box on Black Cat has been demolished.
  • Excavation for the west side headwall complete.
  • Headwall is installed.
  • Precast box fabrication ongoing.
  • Southwest corner of Ustick and Black Cat irrigation work started.
Share February 14, 2025 on Facebook Share February 14, 2025 on X (formerly Twitter) Share February 14, 2025 on Linkedin Email February 14, 2025 link

This project is substantially complete.