February 20, 2025
- Black Cat Road is closed south of Ustick Road.
- Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
- Irrigation and seepage bed installation is ongoing.
- Roadway and sidewalk demo and prep is ongoing.
- Eight Mile irrigation box on Black Cat has been demolished.
- Excavation for the west side headwall complete.
- Irrigation work on Nine Mile and Rutledge has started.
- Headwall at Rutledge complete.
- Precast box fabrication complete for this season.
- Southwest corner of Ustick and Black Cat (Eight Mile) irrigation work ongoing.