February 20, 2025

  • Black Cat Road is closed south of Ustick Road.
  • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
  • Irrigation and seepage bed installation is ongoing.
  • Roadway and sidewalk demo and prep is ongoing.
  • Eight Mile irrigation box on Black Cat has been demolished.
  • Excavation for the west side headwall complete.
  • Irrigation work on Nine Mile and Rutledge has started.
  • Headwall at Rutledge complete.
  • Precast box fabrication complete for this season.
  • Southwest corner of Ustick and Black Cat (Eight Mile) irrigation work ongoing.
Share February 20, 2025 on Facebook Share February 20, 2025 on X (formerly Twitter) Share February 20, 2025 on Linkedin Email February 20, 2025 link

This project is substantially complete.