February 27, 2026

  • Black Cat remains closed south of Ustick Rd.
  • Concrete paving section and sidewalk placements remain.
  • City of Meridian sewer and water line installation is complete. Water Control Vault commissioning work is ongoing. Underground Electrical work and signal pole bases are complete. Final remaining sections of concrete median islands, curb and gutter/sidewalk, along the eastern portion of Ustick, starting next week.