February 28, 2025

28 Feb 2025
  • Black Cat Road is closed south of Ustick Road.
  • Ustick remains open: Traffic has been shifted onto the temporary asphalt on the south side of Ustick – one lane in each direction.
  • Irrigation and seepage bed installation is ongoing.
  • Roadway and sidewalk demo and prep are ongoing on the north side of Ustick.
  • Eight mile irrigation: Excavation for the west side diversion structure complete.
  • Utility relocations are nearly complete.
  • Temporary precast sections have been set.
  • Irrigation work on Nine mile and Rutledge continues.
  • Headwall at Rutledge complete.
  • Precast box fabrication complete for this season.