February 5, 2026

  • Black Cat remains closed south of Ustick Rd.
  • Concrete paving section, curb, gutter and sidewalk placements are nearly complete.
  • Remaining sections include the south side of Ustick and Black Cat.
  • Asphalt paving along Ustick complete and nearly all lanes have been marked.
  • Ustick and Black Cat signal swap to final configuration was completed this week.
  • City of Meridian sewer and water line installation is complete.
  • Placing nine pole bases this week for signals.
Share February 5, 2026 on Facebook Share February 5, 2026 on X (formerly Twitter) Share February 5, 2026 on Linkedin Email February 5, 2026 link

This project is substantially complete.

<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>