February 7, 2025

  • Black Cat Road is closed south of Ustick Road.
  • Traffic has been shifted onto the temporary asphalt on the south side of Ustick.
  • Irrigation and seepage bed installation is ongoing.
  • Roadway and sidewalk demo and prep is ongoing.
  • Eight Mile irrigation box on Black Cat has been demolished.
  • Excavation for the west side headwall complete.
  • Headwall is installed.
  • Precast box fabrication ongoing.
Share February 7, 2025 on Facebook Share February 7, 2025 on Twitter Share February 7, 2025 on Linkedin Email February 7, 2025 link
<span class="translation_missing" title="translation missing: en-US.projects.blog_posts.show.load_comment_text">Load Comment Text</span>