January 16, 2026
- Eightmile and Ninemile irrigation:
- Irrigation work is ongoing at both Eightmile and Ninemile. Work is nearly complete.
- Ninemile north headwall placed and backfilled. Eightmile has been backfilled.
- Curb, gutter and sidewalk placements ongoing on the south side of Ustick.
- Patterned concrete median islands are being placed east of Black Cat.
- Asphalt paving portions of the north and south side of Ustick complete.
- Weather dependent, the contractor is working towards having the remaining paving sections on Ustick complete in the next couple of weeks.
- City of Meridian sewer and water line installation is complete.
- East headwall of Eightmile has been placed and backfilled.