January 23, 2026
- Eightmile and Ninemile irrigation: Irrigation work: Ninemile complete.
- Eightmile complete.
- Curb, gutter and sidewalk placements are nearly complete.
- Remaining sections include the east end of the project along Ustick – minimal work remains.
- Patterned concrete median islands have been placed along Ustick – work ongoing on the south side of Black Cat.
- Asphalt paving along Ustick complete and nearly all lanes have been marked.
- Ustick and Black Cat signal swap to final configuration was completed this week.
- City of Meridian sewer and water line installation is complete.
Share January 23, 2026 on Facebook
Share January 23, 2026 on X (formerly Twitter)
Share January 23, 2026 on Linkedin
Email January 23, 2026 link
This project is substantially complete.